This investigation spins off from an ongoing attempt to understand Vancouver’s Property Endowment Fund. The appended table provides ready, organized access to key city reports that outline expenditures on Southeast False Creek and Olympic Village. With each additional financial commitment, this phrase gets repeated: “Source of funding to be the Property Endowment Fund.”

A December 2008 report states: “The budget for the work completed or currently underway is approximately $110 million” (p. 2). That figure falls within the broad neighborhood of the $134 million calculated from reports in the appended table.

A total of $153.4 million for “site serving and amenity costs” is projected in an undated factsheet (apparently from 2008) titled Financing Plan for Southeast False Creek – Including the Olympic Village. The same figure of $153.4 million is cited earlier in Property Endowment Fund Pro Forma Update of October 2006. Page 9 offers this remark:

The net present value of the PEF expenditures in SEFC are currently $153.4 million – an increase of approximately 66% since the 2005 pro forma. [emphasis mine]

This suggests that at least $40 million more is yet to be spent on the SEFC site.
 

       
Dollars*
       
       
Date
       
       
Link to Report
       
       
Description
       
       
002,309,000
       
2006 May
       
20060502-a6.pdf
       
Six construction consultants (Morrow, Stantec, PWL, Levelton, Hayco, FVB)
       
019,309,000
       
2006 May
       
20060502-a6.pdf
       
Nine prior approvals (incl. Stantec, JJM, Ruskin, Quantum, Geopac, HAZCO)
       
007,847,000
       
2006 June
       
20060627-a14.pdf
       
Roads and utilities (BelPacific)
       
003,695,000
       
2006 July
       
20060711-a17.pdf
       
Steel sheet pile bulkhead and steel pipe piling (Fraser River Pile and Dredge)
       
001,000,000
       
2006 July
       
20060718-a19.pdf
       
Interim site servicing
       
005,483,000
       
2006 July
       
20060718-a19.pdf
       
Contract for shoreline construction (JJM)
       
000,500,000
       
2006 Dec
       
20061212-a32.pdf
       
Contract for supply of granite blocks (Bedrock Granite)
       
014,000,000
       
2007 Apr
       
20070501-a7.pdf
       
Contract C107 for waterfront construction (Wilco)
       
029,000,000
       
2007 June
       
20070626-a11.pdf
       
SEFC Community Centre design and budget
       
023,000,000
       
2007 July
       
20070724-a29.pdf
       
Contract C111 for First Avenue reconstruction (BelPacific)
       
010,770,000
       
2008 Jan
       
20080131-csb1.pdf
       
Salt Building restoration (Ruskin and SBR Corp)
       
001,500,000
       
2008 Feb
       
20080311-a3.pdf
       
Site servicing
       
000,245,000
       
2008 Feb
       
20080311-a3.pdf
       
Occupational health and safety coordination (Ian Mayall and Millenium)
       
004,200,000
       
2008 Feb
       
20080311-a3.pdf
       
Previous interim site requests p. 3 [20050512, 20061116, 20070130, 20070624]
       
008,500,000
       
2008 Sept
       
20080930-a17.pdf
       
Contract C113 for streetscape construction (Wilco)
       
003,000,000
       
2008 Dec
       
20081216-a11.pdf
       
Contingency for public spaces and infrastructure
       
       
134,358,000
       
       
 
       
       
 
       
       
Total as of 2009 Feb
       
xxxxxxxxxxxxxxxx
       
xxxxxxxxxxxxx
       
xxxxxxxxxxxxxxxxxxxxxx
       
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

* Dollars rounded to nearest thousand

Investigation produced February 2009