“Regular” Olympic Village Funding
This investigation spins off from an ongoing attempt to understand Vancouver’s Property Endowment Fund. The appended table provides ready, organized access to key city reports that outline expenditures on Southeast False Creek and Olympic Village. With each additional financial commitment, this phrase gets repeated: “Source of funding to be the Property Endowment Fund.”
A December 2008 report states: “The budget for the work completed or currently underway is approximately $110 million” (p. 2). That figure falls within the broad neighborhood of the $134 million calculated from reports in the appended table.
A total of $153.4 million for “site serving and amenity costs” is projected in an undated factsheet (apparently from 2008) titled Financing Plan for Southeast False Creek – Including the Olympic Village. The same figure of $153.4 million is cited earlier in Property Endowment Fund Pro Forma Update of October 2006. Page 9 offers this remark:
The net present value of the PEF expenditures in SEFC are currently $153.4 million – an increase of approximately 66% since the 2005 pro forma. [emphasis mine]
This suggests that at least $40 million more is yet to be spent on the SEFC site.
Dollars* |
Date |
Link to Report |
Description |
002,309,000 |
2006 May |
20060502-a6.pdf |
Six construction consultants (Morrow, Stantec, PWL, Levelton, Hayco, FVB) |
019,309,000 |
2006 May |
20060502-a6.pdf |
Nine prior approvals (incl. Stantec, JJM, Ruskin, Quantum, Geopac, HAZCO) |
007,847,000 |
2006 June |
20060627-a14.pdf |
Roads and utilities (BelPacific) |
003,695,000 |
2006 July |
20060711-a17.pdf |
Steel sheet pile bulkhead and steel pipe piling (Fraser River Pile and Dredge) |
001,000,000 |
2006 July |
20060718-a19.pdf |
Interim site servicing |
005,483,000 |
2006 July |
20060718-a19.pdf |
Contract for shoreline construction (JJM) |
000,500,000 |
2006 Dec |
20061212-a32.pdf |
Contract for supply of granite blocks (Bedrock Granite) |
014,000,000 |
2007 Apr |
20070501-a7.pdf |
Contract C107 for waterfront construction (Wilco) |
029,000,000 |
2007 June |
20070626-a11.pdf |
SEFC Community Centre design and budget |
023,000,000 |
2007 July |
20070724-a29.pdf |
Contract C111 for First Avenue reconstruction (BelPacific) |
010,770,000 |
2008 Jan |
20080131-csb1.pdf |
Salt Building restoration (Ruskin and SBR Corp) |
001,500,000 |
2008 Feb |
20080311-a3.pdf |
Site servicing |
000,245,000 |
2008 Feb |
20080311-a3.pdf |
Occupational health and safety coordination (Ian Mayall and Millenium) |
004,200,000 |
2008 Feb |
20080311-a3.pdf |
Previous interim site requests p. 3 [20050512, 20061116, 20070130, 20070624] |
008,500,000 |
2008 Sept |
20080930-a17.pdf |
Contract C113 for streetscape construction (Wilco) |
003,000,000 |
2008 Dec |
20081216-a11.pdf |
Contingency for public spaces and infrastructure |
134,358,000 |
|
|
Total as of 2009 Feb |
xxxxxxxxxxxxxxxx |
xxxxxxxxxxxxx |
xxxxxxxxxxxxxxxxxxxxxx |
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx |
* Dollars rounded to nearest thousand
Investigation produced February 2009